This was another busy and productive week with a lot of work beging completed on Edgewater and Walnut. As work is wrapping up on Edgewater construction on Wilcox will begin.

Work Completed This Week

  • Drive approaches were completed on Edgewater.
  • Final grading and paving of the first course of pavement on Edgewater from Wilcox to Thompson.
  • Sanitary sewer was completed on Walnut and Thompson.
  • Water main installation was completed on Walnut and Thompson and testing of the main has begun.

Anticipated Work

  • Water main testing will be completed and connection of the main to the water system will be completed early week.
  • Water service installation on Thompson and Walnut will begin.
  • Paving of the top course of asphalt on Edgewater is scheduled for Tuesday.
  • Removal of the roadway on Wilcox is scheduled for Thursday. The removal will consist of crushing the roadway which turns the roadway into gravel. This gravel will remain in place over the weekend.

Once final paving is completed on Edgewater between Wilcox and Thompson, Wilcox will be closed to through traffic. All traffic into and out of the neighborhood must use Edgewater.