Pipestone Road Update: All the sanitary sewer work in Pipestone Road has been completed and the road has been paved. Pipestone Road will be reopened to traffic Monday afternoon after pavement markings have been installed.

Lift Station: The Conrail Lift Station start up has occurred and the station is now in service, handling wastewater from the Pipestone Road sewer! The former Pipestone lift station has been demolished. Punchlist items on the lift station will continue to be addressed over the next several weeks.

Upcoming Work: Work on the 21” gravity sewer near the truck wash will resume next week. Preparations for the proposed sewer crossing under I-94 have encountered some unanticipated challenges with difficult soil and groundwater issues. Alternative methods for installing the highway crossing are under consideration with the contractor and MDOT.