This Week:

  • DeSal Excavating installed water service stubs to each home the first half of this week. Homeowners may now begin to schedule the water service connection into the house with the contractor they selected.
  • DeSal Excavating replaced the aggregate base of the road where it was impacted by water main construction.
  • Dewatering equipment was removed from the site, DeSal is working on getting the dewatering treatment system removed in the next week.
  • DeSal Excavating began general project clean up.

 

Next Week:

  • DeSal Excavating will remove the existing asphalt out to the road centerline on Tuesday in the lanes of road which will be repaved.
  • Black Gold (DeSal’s paving subcontractor) is scheduled to be on site Wednesday to complete the road paving.
  • DeSal Excavating will work on lawn restoration next week.

 

Please contact any project representative if you have questions or concerns.