Progress Report:
- Sanitary Sewer main and new sewer services are complete in Sanford between Broadway and Summit
- New water main installed in Sanford between Broadway and almost to Summit
- New water main installed in Columbia between Sanford and almost to Peck
- Completed the last few water services in Sanford south of Summit to the new water main
Upcoming Work:
- Last water main tie-in at Sanford and Oakwood is currently scheduled for Thursday, May 8, 2025. This will create a short water disruption for customers along Oakwood between 6th and Sanford and the 3200 block of 5th Street.
- When water flow is disrupted from connections or valve exercising, customers may experience air in their water lines and discolored water. Be sure to flush all lines, but especially the cold water through a bathtub or faucet without a screen and run until the water is clear.
- On Monday, May 5, the road will begin to be rebuilt on Sanford south of Summit. This involves removing roughly 1-foot of surface there is now, compacting the sand and then placing compacted gravel for a good road base. Access will be difficult until the gravel is placed.
- Once gravel is placed on all 3 blocks of Sanford, new concrete curb and gutter will be installed, likely the week of May 12
- Remove the remaining roadway on Columbia between Sanford and Peck
- New storm drainage structures and pipe on Sanford between Broadway and Summit