Progress Report:
- The water service for the pump station building was installed.
- The new force main was successfully pressure tested.
- The road subbase was graded and compacted.
- The gravity sewer is being installed today.
Upcoming Work:
- Concrete base course and aggregate base will be placed in preparation for repaving the road.