Work completed/in progress from this past week:

  • Kamminga & Roodvoets was awarded the contract for the road improvements between Division and River.
  • Lakewood closed between 160th and 152nd. Traffic detoured to James Street.
  • Lakewood closed between 152nd and 144th. Traffic detoured to Ottawa Beach.
  • Lakewood closed between 144th and River. Traffic detoured to Douglas/Ottawa Beach.
  • 36″ transmission main construction progressed to 152nd Ave.
  • Drilling contractor continues to remove material for pipe installation beneath Pine Creek.
  • HDPE pipe welded and staged for drilling.
  • Water service verification and replacement, as necessary.
  • Road building behind transmission main installation continues.
  • Partial road removal between Division and Aniline completed.

 

Anticipated activities for next week include:

  • Second water main crew will be on-site.
  • 152nd Avenue intersection will be closed and transmission main will be installed across intersection.
  • Temporarily shut down section of Park Township water main west of 152nd for modifications and install a new hydrant.
  • Begin transmission main installation between 144th and Aniline.
  • Drilling contractor will continue to remove material for pipe installation beneath Pine Creek.
  • Water service and sanitary lateral verification and replacement.
  • Dewatering setups as necessary.