Progress Report

This week:

  • Dykema completed water service stub installation on Bent Tree Ridge.
  • Dykema continued water service stub installation on Wolven Avenue.
  • Dykema started water main installation on 11 Mile Road.

Next week:

  • Dykema will continue water main construction on 11 Mile Road.
  • Dykema will continue water service stub installation on Wolven Avenue.
  • Dykema will start water service stub installation on Stoneridge Drive.

 

Please contact a project representative if you have questions or concerns.

 

What to Expect

May

  • Water main construction to begin in 11 Mile Road.
  • Water service installation along Wolven Avenue and Stoneridge Drive.
  • Pressure test and disinfect newly installed water main in the 43 North Neighborhood.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.

Long Term

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • May
    • Water service installation on Wolven Avenue south of 43 North entrance
    • Bent Tree Ridge Drive restoration
  • May – June
    • Stoneridge Drive water service installation and restoration
  • May – July
    • 11 Mile Road water main and water service installation
  • June – July
    • 43 North water service installation and restoration
  • July – August
    • Elstner Avenue water main and water service installation