This week:

  • Schippers installed new water services on Rockhill Drive.
  • Schippers completed the final water main tie-in on Rockhill Drive.
  • Schippers completed the water main tie-in on Bonanza Drive at 5 Mile Road.
  • Schippers began installing new water services on Bonanza Drive and Bonneville Drive.
  • Tree clearing was completed in the water main easement between Bonneville Drive and Rockvalley Drive.

Next week:

  • Water service installation in Bonanza Drive and Bonneville Drive will continue.
  • Once all of the water services have been switched from the temporary water main to the new water main, Schippers will disassemble the temporary water main and start installing it north of Brisam Street.

 

Please contact a project representative if you have questions or concerns.

 

What to Expect

End of May to Beginning of June
  • Water service installation on Bonneville Drive and Bonanza Drive between 5 Mile Road and Brisam Street.
Long Term
  • Schippers’ overall project schedule anticipates that the total project, including road paving and lawn restoration, will be complete in late summer. Schippers is currently on track to meet this schedule.

 

There will be times that the area in front of your homes is torn up and you will have limited access to your home. Please let us know if you have any special access needs and we will do our best to make arrangements with you.

The contractor has set up a bank of temporary mailboxes on Brisam Street, west of Bonneville Drive. If you are within the construction area, your mail service has been temporarily relocated to here. The contractor is also coordinating with the trash haulers in the area to ensure that the trash is picked up during construction. Please bring your cans to the end of your driveway as you typically would, and the contractor will move them as necessary for pickup and return them at the end of the day.

 

Projected Timeline

  • May 
    • Water service installation on Bonneville Dr. and Bonanaza Dr. between 5 Mile Rd. and Brisam St.
  • June
    • Water service construction along Plainfield Ave.
    • Road reconstruction in Rockhill Dr.
    • Water main and water service construction in Rockvalley Dr.
  • Late-June – late-September
    • Water main and water service construction on Bonneville Dr. and court streets north of Brisam St.