Work Completed (April 31 – May 21)

  • Work continued on the restroom building including installation of sills.
  • Concrete pavement has started under the pavilion with installation of the circle banding.
  • All concrete walls are now poured.
  • Site furniture has been assembled and is currently being stored, will installed following completion of major site activities.
 

Anticipated Work Next Week (Weather dependent)

  • Concrete around the pavilion and restroom building will be nearly complete by the end of the week. This will be done in time to allow for final work on the Pavilion to being the week of June 1.
  • Final work on the restroom building will continue with a goal of final inspections within the next week or two.