Progress Report: This week Miller Bridge started to set the “H” piles in the Bayou for the bridge expansion. These will support the bike lane and observation bumpouts. In addition, they continue to work on the pathway, digging topsoil, grading and placing gravel.
Upcoming Work: Next week work will continue on the “H” piles and continuing to grade out the path between 144th Avenue and the Green Street Bridge.© 2024 Prein&Newhof, All Rights Reserved