This week the focus was on road rebuilding on Center Street.
Work Completed This Week on West
- The new water main was connected at Vine Street.
Work Completed This Week on Center
- Road rebuilding continued with aggregate placement over the entire length.
- Curb and gutter was installed at the intersections.
- Milling of the south bound lane was completed.
Anticipated Work on Center
- Final grading will be completed on Tuesday.
- Paving of the first course of asphalt is scheduled for Wednesday, May 29.
- Preparation for drives, spreading topsoil and structure adjustments will follow paving.
Anticipated Work on West
- Water service replacements will start up again on Thursday.