Road rebuilding was the primary focus this week now that all underground work is complete. Tinkham is starting to look like a road again!
Work Completed This Week
- Sidewalk ramps and all remaining concrete from Lakeshore to Gaylord were completed.
- Final gravel was placed and graded from Lakeshore to Gaylord.
Anticipated Work Next Week
- The first course of asphalt west of Gaylord is scheduled to be placed on Wednesday, May 29.
- Grading the sand for placement of gravel east of Gaylord will start and gravel placement may begin near the end of the week.