- Montgomery moved materials and some equipment on site and began locating existing underground utilities.
- Montgomery also began moving underground irrigation systems out of the way of construction and will ensure that they are properly reinstalled after construction is complete.
Next Week:
- Montgomery will move equipment to the site and begin stripping topsoil on Tuesday.
- Water main construction will begin next week.