Work Completed This Past Week:

  • Crews have completed installing water main in Leahy between Sherman and Barney

 

Work Anticipated Week of May 29, 2023

  • No work will take place on Monday, May 29, 2023 for the Memorial Day Holiday
  • Water Services are being scheduled for replacement between Sherman and midblock between Hume and Hovey
  • Water main will be tested, cleaned and sampled for connection between Hovey and Barney
  • New water Main will be connected and made live to Barney
  • Additional water main will be installed in Hume between Baker and Leahy

 

Work Anticipated Week of June 5, 2023

  • Water services will be replaced between the new water main and the homes
  • Water main will be placed between Baker and Leahy in Hume
  • Storm Sewer may begin to be replaced