This Week:

  • The existing asphalt road was pulverized on Friday in preparation for construction to start on Tuesday after the holiday.
  • Marksman (Kamminga & Roodvoet’s bore & jack subcontractor) started moving in their equipment in preparation for construction to start next week.

 

Next Week:

  • Kamminga & Roodvoets (K&R) will be on site Tuesday to start water main and sanitary sewer construction.
  • Northville Drive will be closed to thru traffic between Lakehurst Drive and Leelanau Drive.

 

Please contact any project representative if you have questions or concerns.