Work completed/in progress from this past week:

  • 36″ transmission main construction progressed through 152nd Ave. Intersection remains closed.
  • Drilling contractor continues to remove material for pipe installation beneath Pine Creek.
  • Water service and sanitary lateral verification and replacement.
  • Second pipe crew began transmission main construction east of 144th Ave.

 

Anticipated activities for next week include:

  • Pave 152nd Ave intersection and reopen to traffic.
  • Pressure test and disinfect transmission main between 160th and 152nd.
  • Continue transmission main installation east of 144th.
  • Drilling contractor will continue to remove material for pipe installation beneath Pine Creek.
  • Water service and sanitary lateral verification and replacement.
  • Mill north side of Lakewood between 152nd and 144th.