Progress Report

This week:

  • Dykema completed water service stub installation on Wolven Avenue.
  • Dykema continued water service stub installation on Stoneridge Drive.
  • Dykema completed water main installation on 11 Mile Road.

Next week:

  • Dykema will pressure test and disinfect the water main along 11 Mile Road.
  • Dykema will finish water service stub installation on Stoneridge Drive.
  • Dykema will start water service stub installation in the 43 North neighborhood.

 

What to Expect

June
  • Water service installation in the 43 North neighborhood.
  • Pressure test and disinfect newly installed water main along 11 Mile Road.
  • Installation of water services on private property. This work will be coordinated between each individual property owner and the contractor you select to install your water service.
Long Term

Dykema’s overall project schedule anticipates the total project, including road paving and lawn restoration, being complete in late August 2021. Dykema is currently ahead of this schedule and on track to complete the project in August.

 

Projected Timeline

  • June
    • Wolven Avenue and Bent Tree Ridge road reconstruction
    • Stoneridge Drive water service installation and restoration
  • June – July
    • 43 North water service installation and restoration
  • Late June – early July
    • 11 Mile Road water service installation
  • July – August
    • Elstner Avenue water main and water service installation