DeSal Excavating continued installing water main along House Street. As of late this week, they are approximately 2,100 feet east of Pine Island, with an average installation rate of 300 feet – 400 feet per day.

 

What to Expect Next Week (June 1 – 6)

  • DeSal will continue installing water main along the north/west side of House Street. By the end of the week, the water main should be past the Belmont Armory driveway and nearing Imperial Pine Drive.
  • DeSal plans to work with the Plainfield Water Department to pressure test and disinfect the first section of water main.
 

Projected Timeline

  • May-June
    • Water Main installation along House Street
  • July
    • Water main installation complete; begin road reconstruction
  • August
    • Road reconstruction