Water service stubs – to the edge of the road right of way – were completed in the south half of the neighborhood this week.

Bultsma also started directional drilling water service stubs under the road at the north end of Lady Lauren.

One house on Royal Hannah was connected to the water municipal water system recently. Note that properties will not show up as “connected” on the construction status map until all paperwork has been submitted and processed.

Concrete driveway replacement is underway.

 

What to Expect Next Week (June 1 – 6)

 

Projected Timeline