Work that took place this week: De-watering for the water main installation began between McCracken and Estes. The de-watering water is being monitored closely to ensure the site is safe for the workers when excavating and safe for the environment. Topsoil is being stripped and stockpiled. More water main pipe and fittings arrived to the site and some water main has been installed near Frisbie and Lakeshore. We do not expect any work to take place, Saturday, May 4, but Saturday work is very likely later in the project.

Here is what to expect next week, the week of May 6, 2019:

Water main will be installed in separate areas on the project.
Some gas main relocation will likely take place