Dykema has completed installation of the transmission main piping with the exception of the tie-in at the pump station. The Plainfield Water Department is working with Dykema to pressure test and disinfect the new pipe over the course of the next week.

The Township is taking advantage of the opportunity to install water services into parcels along Kuttshill that currently do not have a water service stub installed. Dykema is completing this work for the Township this week. Residents are not required to connect as part of this project, but if interested should reach out to the Township Water Department to get more details about connecting.

The final tie-in at the pump station will take place the week of May 13. Over the next two weeks Dykema will begin working on road restoration and lawn restoration along Kuttshill Drive. Driveway restoration will take place when Kuttshill Drive is paved.