Paving was delayed this week but significant progress still was made on the east half of the project with preparation for curb and gutter.
Work Completed This Week
- Sand grade was established from Gaylord to Williams.
- Aggregate was placed from Gaylord to approximately St. Paul.
Anticipated Work Next Week
- Paving of the first course of asphalt west of Gaylord is scheduled for June 4.
- Preparation for curb will continue with placement of gravel east of Gaylord.
- Curb and gutter is tentatively scheduled to begin near the end of the week east of Gaylord.