This week started out slow with preparation work but picked up speed as the week progressed with continued work on sanitary sewer.

Work Completed This Week

  • Water service replacement continued on Thompson and Walnut.
  • Concrete removals were started on Wilcox.
  • Sanitary sewer on Wilcox was started at Edgewater working west.
  • Thompson sanitary sewer was abandoned.
  • Connection to the water main on Plum Street at Thompson will be completed this Saturday.

Anticipated Work

  • Water service replacement will continue on Thompson.
  • Sanitary sewer installation will continue on Wilcox working west from Edgewater.
  • Grading of the sand for placement of gravel on Thompson and Walnut will begin.