Road rebuilding and restoration continued on Jefferson and Dryden this week. Additionally, water main installation has begun moving south on Dryden. The focus next week will continue to be on water main installation on Dryden, as well as, installing the first layer of asphalt on Jefferson and Dryden, north of Jefferson.
Work Completed This Week
- Installation of water main on Dryden street, at the Jefferson Street intersection.
- Installation of sidewalk ramps on Jefferson and Dryden.
- Preparations for the first layer of asphalt on Jefferson or Dryden.
- Yard restoration has begun on Hart, Jefferson and Dryden.
Anticipated Work Next Week
- Water main installation on Dryden south of Jefferson.
- Base layer of asphalt installation on Jefferson and Dryden, north of Jefferson, is currently scheduled for Wednesday, June 5th.
- Sidewalk removal will begin on Dryden south of Jefferson.