Progress Report:
Miller Bridge has been driving the H-Piles for deck expansion of Green St. bridge over Stearns Bayou working from west side to east side. Four piles have been driven to bearing capacity.
In addition, they have continued work on pathway grading, working east towards the bridge. Driveways are being removed and replaced with gravel as they get to them.
Upcoming Work:
Next week crews will continue to drive H-Piles into Stearns Bayou for bridge deck expansion.
Miller Bridge anticipates that they will complete pathway grading between 144th Avenue and the bridge. At that point they plan to begin work on pathway grading on east side of bridge