This Week:

  • Utility relocation work continued around Herrington Avenue in preparation for the road to be lowered at this intersection.
  • Road work was completed on the north half of 10 Mile Road between Algoma Avenue and Jewell Avenue.
  • Brenner Excavating began installing water services at Jewell Avenue and worked west.
  • Brenner Excavating began installing groundwater dewatering system between Freska Pines and Ammerman.

 

Next Week:

  • Brenner Excavating will finish setting up the groundwater dewatering system so that water main construction can continue to the west.
  • Road work will continue near Jewell Avenue.

 

Please contact any project representative if you have questions or concerns.