Work Completed to This Past Week:

  • All water main and water service work was completed with the final tie-ins at 8th & Oakwood and 8th & Summit – THANK YOU For your patience!
  • All storm drainage work has been completed
  • Road building crews are now in town and they are removing material to rebuild a quality road with 8-inches of compacted road gravel

 

Work Anticipated Week of May 8, 2023

  • Finish grading, placing road gravel and compacting and shaping it in place
  • Begin concrete curb and gutter installation – This will be difficult because it will require NO ACCESS to driveways for several days after the concrete is poured.  You may walk on the concrete within a few hours, but driving on it within the first 5 days will risk breaking the concrete.
  • Concrete Driveway approaches will begin to be  poured
  • Concrete sidewalk will be poured along with crosswalk ramps

 

Work Anticipated Week of May 15, 2023

  • Finish any remaining concrete
  • Grading the pavement for the first course of asphalt
  • Begin restoration with backfilling behind concrete curb and gutter, behind sidewalks, etc.