Work Completed This Past Week:

  • Crews lowered manhole covers in the road
  • Milling machines removed the asphalt from the road and took the road down to the gravel road base material
  • Concrete curb and gutter is being removed throughout the project limits on Leahy between Sherman and Broadway
  • Areas of removal have been marked and measured
  • Materials were delivered to the job site

 

Work Anticipated Week of May 8, 2023

  • Work will begin Monday with new water main pipe being placed starting at Sherman
  • Once crews install pipe up to Hume Avenue, they will work to get that first block tested to be tied in to the existing system
  • Crews will continue laying new water main pipe up to Barney
  • Removal of concrete curb and gutter, driveway approaches, sidewalk and ramps will continue

 

Work Anticipated Week of May 15, 2023

  • The first tie-in of new water main could take place at Sherman.  Residences will be notified prior to losing water
  • Water Service lines will begin to be replaced in the first block between Sherman and Hume
  • Water main pipe will continue to be placed up to Barney and in Hume between Baker and Leahy