This Week:

  • DeSal Excavating completed water main construction.
  • Prein&Newhof handed out water service stakes. Please place this stake in your front yard by early next week where you want your water service installed.

 

Next Week:

  • DeSal will pressure test and disinfect the new water main.
  • Pending passing test results, the new water main will be connected to the existing water main the second half of the week.
  • Water service installation will begin after the connection(s) have been made to the existing water main.

 

Please contact any project representative if you have questions or concerns.