Work completed/in progress from the past week:

  • 36″ transmission main construction progressed west entrance of Waukazoo Elementary.
  • Pilot hole for Pine Creek crossing was completed. Contractor will start removing material for pipe installation.
  • Road building continued behind the pipe installation.
  • West entrance to Waukazoo Elementary closed. All school traffic has been directed to the east parking lot.

 

Anticipated activities for next week include the following:

  • Continue transmission main construction, water service verification and replacement, and road building.
  • Continue removing material for HDD pipe installation.
  • Waukazoo school traffic to continue using the east parking lot.