Work Completed This Week

  • Approximately 1,000 feet of storm sewer was placed in addition to 21 storm structures.
  • The water main south of Strong Avenue passed pressure and bacteria testing this week.
  • The water main tie-in at Strong & Peck was made.
  • 14 water services were connected to the new water main.
  • The  storm sewer mainline and sanitary sewer pipe was inspected with closed-circuit television (CCTV).

 

Anticipated Work Next Week

The prime contractor anticipates:

  • Continue directional boring and connecting water services.
  • Continue installing storm sewer.

 

The Contractor is not working on Saturday, May 10, 2021.

 

Phase 2 Scheduling

Kamminga & Roodvoets has an opening in their schedule and is planning to begin Phase 2 (Southern Avenue to Laketon Avenue) earlier than originally planned. Road removal for Phase 2 has been rescheduled to begin approximately Wednesday, May 19 with sanitary sewer installation to follow shortly thereafter. This will not have an impact on the schedule for Phase 1 which is planned to be completed and open to traffic before the end of June 2021.