Progress Report:
- Ron Meyer & Associates continued stripping topsoil and placing sand/gravel this week heading south on 74th Avenue. A second crew was onsite at the end of the week to begin installing storm sewer on 76th Avenue.
- Riverworks Construction finished building the head and wingwalls for all four boardwalks on 76th Avenue.
Upcoming Work:
- Ron Meyer & Associates will continue stripping topsoil and placing sand/gravel heading south on 74th Avenue but will stop when they get to the school to wait until summer vacation. Work will also continue on storm sewer along 76th Avenue, dependent on weather and contractor availability.
- Utilities in the way of the path will also be moved in the coming weeks.