Work completed this week:

  • N Court St – Concrete crews poured the curb and gutter & ADA ramps at intersections.
  • S Court St – Road crews removed poor soils from the intersection of S Court/Walnut and replaced with stable sand. Concrete crews poured the curb and gutter & ADA ramps at intersections.
  • Walnut St – Hydrotested force main.
  • Vine St – Completed water main tie-ins at Main Street and installed water services. Road building crews graded the roadway. Concrete crews poured the curb and gutter & ADA ramps.
  • Grove St/Lake St – Crews started installing new water main.

Work anticipated next week:

  • N Court St – Road building crews will fine grade the aggregate base in preparation for paving. Asphalt crews scheduled to be on site Friday, May 16th to pave, weather pending.
  • S Court St – Road building crews will fine grade the aggregate base in preparation for paving. Asphalt crews scheduled to be on site Friday, May 16th to pave, weather pending.
  • Vine St –Remove and replace the curb and gutter & ADA ramps at the southeast corner of Vine/Main. Road building crews will fine grade the aggregate base in preparation for paving. Asphalt crews tentatively scheduled to be on site Friday, May 16th to pave, weather pending.
  • Grove St/Lake St – Crews will continue installing water main.