Progress Report:
This week, Subcontractor T&D Concrete continued installing new sidewalk along Cascade Road and began pouring sidewalk sections along Robinson Road, reaching up to the driveway of Mayflower Congregational Church. Brenner Excavating focused on restoration efforts along Cascade Road, including spreading topsoil and repairing sprinkler systems. Superior Asphalt was also on site, completing hand patching and paving of driveways along Cascade Road.
Upcoming Work:
Next week, Brenner Excavating will resume sidewalk construction along Robinson Road, extending up to Lakeside Drive. Work is also scheduled to begin on the retaining wall near the intersection of Maryland Avenue and Robinson Road.