Last Two Weeks:
  • Water main installation along 11 Mile Road was completed and was connected to the water main installed by Montgomery Excavating earlier in the year. This completes the 12-inch loop along Algoma Avenue and Jewell Avenue from 10 Mile Road to 11 Mile Road.
  • CL Trucking installed water services along 11 Mile Road.
  • Paving along Algoma Avenue and 11 Mile Road was completed.
  • Lawn restoration along Algoma Avenue was completed.
  • The first two private water services were installed (green shaded parcels on above map) and the houses connected to the municipal water system!
Next Week:
  • 8-inch water main installation along Winding Ridge Trail will begin on Monday and will be completed next week.