Progress Report

This week:
  • Dykema worked on restoration throughout the project.
  • Rieth-Riley (Dykema’s asphalt subcontractor) paved the base course of asphalt. They will be back as soon as the weather permits to pave the final top course.
Next week:
  • Final top course paving weather permitting.
  • Dykema will work on final project clean up.

 

What to Expect/Project Timeline

November
  • Road pavement restoration
  • Final project clean up
Spring 2022
  • Lawn restoration will be touched up as a necessary next spring to ensure good grass growth