Al’s Excavating crews were able to continue construction with the great weather this week. Crews formed and poured the remaining concrete curb openings and paved the first of two layers of asphalt on the remaining section of pathway to the bridge. Both Airway Street and Jericho Avenue also had the hydroseeding work completed this week.
Next week, the concrete crew will be back onsite to finish the access ramps at Peter Creek and Ella Terrace Drives. They will also complete final fall punch list items and prepare the pathway for winter. They will resume construction on the south of the Rogue River Bridge to connect to the White Pine Trail next spring.