This past week, the Contractor completed the following work:
- Completed all water service replacements and reconnections to the new water main
- Removed poor soil under Wilshire Drive from in front of address 1116 Wilshire to the south and cul-de-sac
- Installed underdrain pipe to help keep the road bed drained
- Installed new gravel road base material on Wilshire Drive
- Completed water main connections from the new water main to the existing system at Sophia (today) and Peach
**Currently, Peach is closed to through traffic between Sophia and Slocum. Use caution when traveling down Wilshire.**
Anticipated work over the next 2 weeks:
- Monday, 11/21 – finish the last water main connection at Peach and Slocum
- Continue removing poor soil under the roadway and replace with sand and road gravel
- Install additional 200-feet of underdrain on Wilshire from Peach to the curve
- Place first course of asphalt on Wilshire
- Replace driveway approaches