This Week:
- Concrete sidewalk replacement was completed.
- K&R continued general project cleanup.
- Due to the weather, there are some asphalt driveways which were not completed this week. The pavers are scheduled to be back on site early next week to complete this work.
Next Week:
- Paving of remaining asphalt driveways.
- Irrigation repairs and final seeding of all disturbed lawn areas.
Please contact any project representative if you have questions or concerns.