This Week

Martin J was on site early this week to pour the concrete curb, sidewalk, and ADA ramps. This process took two days and is nearly complete. Brenner was on site for final restoration and seeding on Thursday and Friday this week.

 

Next Week

Crews will be on site to install trail signage and pavement markings. They will also begin placing asphalt around the pedestrian island and curbs to match the new concrete. Work is nearly complete; thank you for your patience while we wrap things up!