This week started out a little slow, but ended with a flurry of activity.

 

Work Completed this Week (November 9 – 13)

  • Floor slab for the restroom building was poured.
  • Storm sewer installation began, this has been a slow process due to the many utilities underground but headway is being made.

 

Anticipated Work Next Week

  • Pressure testing and chlorination of the new water main will be completed and will continue into the following week.
  • Storm sewer installation will continue.
  • Installation of auger cast piling for the new pavilion structure is anticipated at the beginning of the week
  • Rough in for the site electrical may begin.