This week, the last of the concrete driveways were completed and asphalt was placed behind the sidewalk where it was disturbed.  The remainder of the asphalt will be completed today.  Roughly a third of the 140+ trees have been planted and backfilling and restoration efforts with topsoil is underway as well.  Irrigation in the blocks between Moon and Torrent has been installed.  Mainline site cleanup is beginning with the preparation of removing the much extended family of Darrel the Barrel.  Pavement markings will be re-done again tomorrow, Saturday as more work will proceed on the job.  Unfortunately, none of the furniture got installed this week.

Here is what to expect the week of November 25, 2019, the week of Thanksgiving.  Although it is a short week next week, if the weather holds, it should be a very productive week.