Work completed/in progress:
- Completed tree clearing.
- Butt-fusing HDPE pipe lengths in preparation for pipe laying.
- Installing dewatering system on MCCRC property north of Apple Avenue.
Anticipated work activities for the coming week:
- Continue butt-fusing HDPE pipe and dewatering system installation.
- Start HDPE pipe installation week of December 2.