Phase 2:
This Week:
- Concrete sidewalk and driveways were completed on Audley Drive and the north half of Daylor.
- Many of the existing concrete driveways which were removed for water main construction were poured under the edge of the existing road. This necessitated that asphalt patches be placed at the end of each driveway impacted. These patches as well as the road patch across Audley Drive were paved this week.
- Montgomery continued to work on punch list items and lawn restoration. However, with the wet weather we had this week not much topsoil work was able to be completed.
Next Week:
- Lawn restoration will continue next week as weather allows.
- Montgomery will work on punch list items and general project cleanup for the winter.