Work Completed Recently
- Deflection testing of the 48-inch sanitary sewer has been completed.
- Air testing of the new sanitary sewer has been completed.
- Sanitary sewer has been televised (videos have not yet been reviewed).
- The flow meter in the Union Pier intersection is operational.
- Work on the remaining punch list items continues.