Work Completed this Week (November 31 – December 4)

  • Pile caps for the auger cast footings for the pavilion were poured and prepped for the pavilion piers.
  • Storm sewer installation continued.
  • The water main was approved and the connection to the City water system at Court Street is nearly complete.
  • The exterior walls of the restroom building were erected.
  • Light pole bases were formed and prepared for concrete.
 

Anticipated Work Next Week

  • Water services will be installed and possibly the water main will be connected at Ludington Avenue which will mark the end of all water main construction.
  • Storm sewer installation will continue.
  • Light pole bases will be poured.