Week 6 is completed and marks the last week of full time work on Southern Avenue!

 

Work Completed Last Week

  • Concrete sidewalk, driveways and ADA ramps were reinstalled on Wednesday.
  • Manhole castings were raised up to final grade.
  • Final asphalt paving was completed this morning (Friday, November 5).
  • Top soil was spread over all disturbed areas in preparation for hydroseeding.

 

Anticipated Work Moving Forward

  • PK Contracting is currently scheduled to install pavement markings on Tuesday, November 9. Southern Avenue will be opened up to traffic after pavement markings are installed next week.
  • Hydroseed will be installed over all disturbed areas.
  • General site cleanup and punch list items will be worked on over the next couple weeks.