This week consisted of prepping for the top course of pavement and driveways. Paving of the top course of the new roadway is scheduled for this Saturday November 6!
Work Completed This Week (November 2 – 6)
- McCormick raised manhole castings and water valve boxes.
- McCormick prepared drive approaches.
- Concrete for driveways was installed.
- Top course of pavement is scheduled for this weekend.
Anticipated Work Next Week
- The drive approaches will be paved between the concrete and the new roadway.
- Topsoil will be placed and seeded
- Pavement striping will be placed if weather permits.