Work completed/in progress:
- Installation of the remaining wall forms was delayed due to rain and high winds this week.
- All wall pipes and conduit are now in place and the wall is nearly ready for concrete.
Anticipated work activities for the coming week:
- The date of the first wall pour is scheduled for next week Wednesday.
- GRC is moving forward with preparing for the second wall pour in the southeast corner of the structure.