Phase 1:
This Week:
- Traffic control devices were removed from Phase 1.
Phase 2:
This Week:
- The beginning of the week was slow due to the rain and Montgomery was not able to get much work done on site.
- Montgomery completed the water main construction on the north half of Daylor Drive. This is where water main construction will end for the year.
- Montgomery pressure tested the new water main on Daylor Drive and is working with the Township Water Department to disinfect the new pipe.
Next Week:
- Concrete crews are scheduled to be on site Monday and will begin driveway and sidewalk replacement on Audley Drive.
- Pending passing test results, water service installation on the north half of Daylor Drive will be completed next week.